Photo credit: SeAH Wind UK
egeplast UK has provided ENATS approved Class 1+ high voltage electric cable duct for the construction of SeAH Wind’s XXL monopile manufacturing facility at Teesworks freeport – the UK’s largest industrial zone.
Located in a 40-metre high and 800-metre long building, SeAH’s new manufacturing facility sits on a 90-acre site and comprises 1.13 million square feet of factory space. It is the first XXL monopile manufacturing facility to be built in the UK.
The site will be used for the production of monopiles up to 120 metres in length, 15.5 metres in diameter and weighing approximately 3,000 tonnes. When fully operational, it is expected to produce between 100 and 200 monopiles per year which will be transported directly from the factory to the new South Bank Quay facility before heading to the North Sea for installation. The construction of SeAH Wind’s XXL monopile manufacturing facility will also create more than 750 jobs at the site.
egeplast UK supplied various sizes of its ENATS Class 1+ black electric cable duct for the project. The company was appointed because its track record in the provision of high quality pipe and ducting systems, and its high levels of customer service. It was also able to make its first delivery to site within 48 hours of its appointment to ensure construction timetables were met.
egeplast’s SDR11 black cable duct products hold the highest technical specification certification issued by the Energy Networks Association (ENATS) and are certified for use in power and cable networks across the UK and Ireland.
Available in diameters ranging from 63mm to 250mm as standard, direct from egeplast UK’s manufacturing facility. Other sizes up to 1600mm are available on request, including the egeplast power Duct for high voltage cables. For more information, contact egeplast UK on 01427 875770 or email sales@egeplast.uk.